Project

Appropriation Request

Appropriation Directed To:

Herbert Hoover Dike Rehabilitation Construction

$77 million

USACOE

Modified Waters Deliveries

$52 million

USACOE

C-44 Reservoir and Stormwater Treatment Areas Construction

$363 million

SFWMD

 

Kissimmee River Restoration/Construction

$31 million

USACOE

Picayune Strand /FAKA Construction

$90 million

SFWMD

Picayune Strand /Merrritt Construction

$40 million

USACOE

C-111 Spreader Canal Construction Project

$70 million

SFWMD

C-51/Stormwater Treatment Area 1 East Construction

$8 million

SFWMD

L31 North Seepage Construction

$5 million

SFWMD

Seminole/Big Cypress Construction Project

$3 million

USACOE

 

 

 

NOTES:

 

The C-43 Reservoir is not an authorized CERP project however, using avenues other than a WRDA process, $473 million is needed to construct this reservoir.

 

Appropriations from this economic stimulus package will not impact crediting issues between the State of Florida and the Federal government until the Comprehensive Everglades Restoration Project is complete

 

 

†††††††††††††††††††††††††††††